Trinity High School - Bond 23 Updates

Construction Plan

The construction timeline for Trinity has multiple phases, allowing school to continue while individual buildings are gradually replaced:

  • Phase 0 (8 months) - Move portable buildings, build new tennis courts, and prepare for major construction phases. Most work is on the south and southeast areas of Trinity's campus.
  • Phase 1 (15 months) - Construction of the new athletics wing and competition gymnasium. Most work is on the southeast area.
  • Phase 2 (22 months) - Construction of the new cafeteria and academic wing. Most work is in the center of campus, with construction support areas to the north and south.
  • Phase 3 (18 months) - Construction of arts wing and performing arts center. Most work is on the northwest part of campus.
  • Phase 4 (4-6 months) - Demolition of remaining buildings; complete remaining work, such as parking lots and landscaping.

Note: All construction timelines are always estimates. Construction timelines can be impacted by many factors, such as extreme weather, supply chain issues, special events, and more.

HEB ISD Bond Election 2023

In November 2023, HEB ISD voters approved a bond that included a proposal to rebuild Trinity High School. The design for the new school preserves the unique character of the "high school on a hill" with impressive outdoor spaces in the middle of campus, while bring improvements to educational spaces and campus safety.